Section 7: Special duty of employers using machinery
This section is inserted by Act No 20 of 2022, section 5.
consolidated text (as at 2013, amended since). juris shows the text as it was consolidated; it does not confirm that this is the law in force today.
7. Special duty of employers using machinery
(1) Where the total power used or generated by machinery
installed at a place of work exceeds 750 kilowatts, the employer
shall employ a registered professional engineer to be in general
charge of all such machinery.
(2) Where the total power used or generated by machinery
installed at a place of work does not exceed 750 kilowatts, the
employer shall employ a competent person to be in general charge
of the machinery.
(3) Every employer who employs a registered professional
engineer under subsection (1) shall, not later than 14 days after the
Acts 2022 647
Registered professional engineer accepts the offer of employment –
(a) inform the Permanent Secretary accordingly, in
writing; and
(b) furnish any document or relevant information as
the Permanent Secretary may require.
(4) A registered professional engineer referred to in
subsection (1) may be employed –
(a) on a full-time basis; or
(b) on a part-time basis, in which case, he shall
not act in such capacity at more than 3 places
of work.
(5) (a) A registered professional engineer employed
under subsection (1) shall, not later than 14 days after accepting an
offer of employment, make an application for registration to be in
general charge of machinery to the Permanent Secretary in the form
set out in the Twenty-First Schedule.
(b) The application under paragraph (a) shall be
submitted together with –
(i) such document or information as the
Permanent Secretary may require; and
(ii) such non-refundable processing fee as
may be prescribed.
(6) (a) The Permanent Secretary may, on receipt of an
application, make such enquiry as he thinks necessary.
(b) The Permanent Secretary may grant or refuse the
application.
(c) Where the Permanent Secretary grants the
application, he shall –
(i) on such terms and conditions as he may
determine; and
648 Acts 2022
(ii) on payment of such registration fee as
may be prescribed,
issue to the applicant a certificate of registration in such form and
manner as he may determine.
(d) Where the Permanent Secretary refuses an
application, he shall inform the applicant accordingly in writing
specifying the reasons of his refusal.
(7) (a) Where there is any change in the particulars of
the certificate of registration of a registered professional engineer in
general charge of machinery, he shall submit a new application as
per subsection (5) to the Permanent Secretary within 14 days of such
change.
(b) Any application submitted under paragraph (a)
will be processed in accordance with subsection (5).
(8) Where a registered professional engineer in general
charge of machinery ceases to practise as a registered professional
engineer in general charge of machinery, he shall notify in writing
the Permanent Secretary of that fact and surrender the certificate
of registration within 14 days of ceasing to practise as registered
professional engineer.
(9) The Permanent Secretary shall keep and maintain a
register of registered professional engineers in general charge of
machinery registered under this section.
(10) A person who is employed as a full-time or part-time
registered professional engineer in general charge of machinery at a
place of work shall not examine any equipment, machinery or plant
specified in sections 51, 52, 53, 54, 57, 58, 59 and 60 at that place
of work, in the capacity of a Registered Boiler Inspector or
Registered Machinery Inspector.
(11) Any employer or registered professional engineer who
fails to comply
gineers in general charge of
machinery registered under this section.
(10) A person who is employed as a full-time or part-time
registered professional engineer in general charge of machinery at a
place of work shall not examine any equipment, machinery or plant
specified in sections 51, 52, 53, 54, 57, 58, 59 and 60 at that place
of work, in the capacity of a Registered Boiler Inspector or
Registered Machinery Inspector.
(11) Any employer or registered professional engineer who
fails to comply with any provision of this section shall commit an
offence.
Acts 2022 649
Ask juris about this section Official source
Questions this section answers
- Do I need a registered professional engineer in charge if my machinery exceeds 750 kilowatts?
- How many days do I have to tell the Permanent Secretary once my engineer accepts the job?
- Can my registered engineer be in charge of machinery at more than one place of work part-time?
- What happens if I don't comply with the rules on employing an engineer for my machinery?