Sugar Industry Efficiency Act · TWELFTH SCHEDULE

consolidated text (as at 2017, amended since). juris shows the text as it was consolidated; it does not confirm that this is the law in force today.

8. Subject to paragraph 9, any applicant shall— (a) endeavour to obtain all necessary clearances and permits, including any Building and Land Use Permit, within a period of 2 years after having been granted authority for land conversion; (b) start the conversion of the land within a period of 6 months from the date on which he obtained the last clearance or permit required for the proposed conversion, failing which the authority shall lapse automatically; (c) complete the project in the manner specified in the authority granted within a period of 5 years from the date on which he obtained the last clearance or permit required for the conversion, failing which the authority shall lapse automatically.