Building Control Act 2012Section 4
4. Exemption from requirement for permit
(1) No permit shall be required for building works relating to –
(a) a gate, hoarding or boundary wall not higher than 1.8
metres, other than –
(i) one which borders a road; or
(ii) an enclosure crossing, or standing within 2
metres of, a watercourse;
(b) a single storey trellis, pergola or gazebo;
(c) a canal or drain not more than 300 millimetres deep;
(d) a temporary stall or shed of lightweight material within
any premises used for the purpose of holding a trade
fair, a fun fair, or an exhibition, lasting not more than 6
months;
(e) the demolition, restoration or reinstatement of a
non-load bearing wall;
(f) the replacement or changing of windows or doors in a
building not exceeding 2 storeys; or
(g) the replacement of existing floor and wall finishes.
(2) Nothing in subsection (1) shall exempt any person from
complying with the other requirements of this Act.
PART II – BUILDING CONTROLADVISORY COUNCIL