21B. Wayleaves
(1) Where the Authority has reason to believe that it
is necessary or expedient for it to lay, and keep installed, water
pipes and appurtenances under or over any land, the owner or
occupier of the land shall be given a notice by the Authority
requiring him to grant the necessary wayleave within a period
not exceeding 21 days.
(2) Where the owner of the land is untraceable, the
Authority shall cause a notice to be posted up in a conspicuous
place on the land for a period of 21 days.
(3) Where there is no response from the owner or
occupier of the land following the issue of a notice under
subsection (1) or (2), the Board may conduct such works
(cid:86)(cid:83)(cid:72)(cid:70)(cid:76)(cid:191)(cid:72)(cid:71)(cid:3)(cid:76)(cid:81)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:81)(cid:82)(cid:87)(cid:76)(cid:70)(cid:72)(cid:3)(cid:68)(cid:86)(cid:3)(cid:76)(cid:87)(cid:3)(cid:70)(cid:82)(cid:81)(cid:86)(cid:76)(cid:71)(cid:72)(cid:85)(cid:86)(cid:3)(cid:81)(cid:72)(cid:70)(cid:72)(cid:86)(cid:86)(cid:68)(cid:85)(cid:92)(cid:3)(cid:68)(cid:81)(cid:71)(cid:3)(cid:72)(cid:91)(cid:83)(cid:72)(cid:71)(cid:76)(cid:72)(cid:81)(cid:87)(cid:17)
(4) Where the owner or occupier of any land who has
been given a notice by the Authority under subsection (1) –
(a) objects or refuses to give the wayleave
before the end of the period of 21 days
or gives the wayleave subject to terms
and conditions not approved by the
Authority; and
232 Acts 2021
(b) where the Authority is unable to reach
an agreement with the owner or occupier
of the land within a period of 60 days
from the date of issue of the notice,
the Authority may apply to the Utility Regulatory Authority
to determine the grant of the wayleave.