Construction Industry Authority Act 2023

Section 129: Protective measures from dangerous or

PART VIIIA: MAINTENANCE OF DANGEROUS, RUINOUS AND HAZARDOUS BUILDINGS

Construction Industry Authority Act 2023Section 129

129. Protective measures from dangerous or ruinous building (1) Where the report under section 128(2) specifies that a building or wall is in a dangerous or ruinous state, the local authority shall cause a notice to be served in accordance with section 154A on its owner or occupier, ordering that, within such time as may be specified in the notice – (a) the building or wall be shored up or otherwise secured, and proper hoardings or fence be put up for the protection of passers-by; (b) the building or wall be forthwith pulled down, secured or repaired; or 746 Acts 2023 (c) the building be vacated. (2) The local authority shall – (a) where a notice sent by registered post on the owner or occupier returns undelivered and personal service of the notice could not be effected on the owner or occupier by the local authority, cause substituted service – (i) by affixing a new notice to the owner’s or occupier’s last known residence or business address; (ii) by affixing a copy of the new notice to the building or wall; and (iii) by publication of the new notice in 2 newspapers, subject to the publication of the new notice in the second newspaper is effected not later than 15 days after the publication of the new notice in the first newspaper; or (b) where the owner or occupier is not known – (i) affix the notice at the building or wall; (ii) cause publication of the notice in 2 newspapers, subject to the publication of the notice in the second Acts 2023 747 newspaper is effected not later than 15 days after the publication of the notice in the first newspaper; and (iii) serve a copy of the notice to the Curator of Vacant Estates under the Curatelle Act, inviting him to confirm, within 30 days of service, whether the building has been vested in him. (3) The notice referred to in subsection (2) shall – (a) order the owner or occupier, not later than such date as specified therein, to pull down, secure or repair the building or wall; and (b) warn the owner or occupier that failure to pull down, secure or repair the building or wall by such date as specified therein, the local authority shall cause the building or wall to be pulled down, secured or repaired. (4) Where an owner or occupier on whom a notice has been served under this section fails to comply with the notice, the local authority shall pull down, secure or repair the building to the satisfaction of the engineer who issued the report under section 128(2). (5) Where – (a) pursuant to subsection (2)(a), the owner or occupier fails to comply with the new notice; or 748 Acts 2023 (b) pursuant to subsection (2)(b) – (i) the owner or occupier fails to comply with the notice; and (ii) the Curator of Vacant Estates confirms that the building has not been vested in him; or (iii) the Curator of Vacant Estates fails to reply to the local authority within 30 days of service of the notice, the Authority shall, notwithstanding any other enactment, cause the building or wall to be pulled down, secured or repaired to the satisfaction of the engineer who issued the report under section 128(2). (6) Any person on whom a notice has been served under this section fails to comply with the notice shall commit an offence and shall, on conviction, be liable to a fine not exceeding 500,000 rupees and to imprisonment for a term not exceeding 5 years. (7) No person shall be prosecuted for failing to comply with a notice served on him under this section as long as the delay granted in the notice has not lapsed.

Came into operation on 1 April 2024 (Proclamation No. 11 of 2024).

as enacted (not consolidated). juris shows this Act from a copy that is not the official consolidation, so it may not carry every amendment; the amendments juris holds are listed. It does not confirm that this is the law in force today.

Ask juris about this section Official source