Environment Act 2024Section 43
43. Review of EIA report
The Director shall review an EIA report submitted by a proponent
and determine its scope and contents and he shall, for that purpose –
(a) request a public department, a non-governmental organisation
or any other person to submit its or his observations
electronically, or in exceptional or unforeseen circumstances,
Acts 2024 117
in such other form and manner as the Director may determine
on the EIA application not later than 14 days after the expiry
of the time limit set for submission of public comments under
section 42(3)(d) or (4);
(b) request the proponent to carry out further study or
investigation, or to submit such additional information,
through the National Electronic Licensing System or in such
other form and manner as the Director may determine, to
ensure that the EIA report is as accurate and exhaustive as
possible; and
(c) set up a technical committee to advise him on the EIA report
or on any aspect of the undertaking.