Light Rail Act 2019Section 12
12. Provisional order for securing compliance
(1) Subject to subsections (5) and (6), where it appears to NLTA that –
(a) a light rail operator is contravening, or is likely to
contravene, any condition of its light rail operator’s
licence;
Acts 2019 611
(b) a light rail operator is not complying with the Code of
Practice, the directions given under section 10 or an
order under section 11; or
(c) the employee of a light rail operator or any agent or
contractor of a light rail operator is contravening, or
is likely to contravene, any condition of the light rail
operator’s licence,
and that it is appropriate or requisite that a provisional order be made
under this section, NLTA shall, instead of taking any decision under
section 13, issue a provisional order to the operator.
(2) A provisional order –
(a) shall require the light rail operator to whom it relates
to do, or not to do, such things as are specified in the
order;
(b) shall take effect at such time, being the earliest
practicable time, as specified in the provisional
order; and
(c) may be revoked at any time by NLTA.
(3) In determining whether it is appropriate or requisite that
a provisional order be made, NLTA shall have regard, in particular,
to the extent to which any person is likely to sustain loss or damage in
consequence of anything which, in contravention of the condition of a light
rail operator’s licence, is likely to be done, or omitted to be done, before a
decision under section 13 may be made.
(4) Subject to subsections (5), (6) and (7), NLTA shall, by notice
in writing, confirm a provisional order, with or without modifications,
where –
(a) NLTA is satisfied that the light rail operator to whom
the order relates –
(i) is contravening, or is likely to contravene, any
condition of his light rail operator’s licence;
612 Acts 2019
(ii) is not complying with the Code of Practice,
directions given under section 10 or order under
section 11; or
(iii) has failed to secure the compliance by its
employees, agents or contractors with any
condition of its light rail operator’s licence; and
(b) the provision made by the order, with any modifications,
is requisite for the purpose of securing compliance with
that condition.
(5) NLTA shall not make or confirm a provisional order in relation
to a light rail operator where it is satisfied –
(a) that the duties imposed on NLTA under this Act
preclude the making of such an order;
(b) that the light rail operator has agreed to take, and is
taking, all necessary steps to secure compliance; or
(c) that the contraventions were of a trivial nature.
(6) Before NLTA makes or confirms a provisional order, it shall
give notice to the light rail operator –
(a) stating that NLTA proposes to make or confirm the
order and setting out its effect;
(b) setting out –
(i) the relevant condition of the light rail operator’s
licence for the purpose of securing compliance
with which the order is to be made or confirmed;
(ii) the acts or omissions which, in NLTA’s opinion,
constitute or would constitute contraventions of
that condition; and
(iii) such other facts which, in NLTA’s opinion, justify
the making or confirmation of the provisional
order; and
Acts 2019 613
(c) specifying the period, not being less than 28 days
after the date of service of the notice, within which
representations or objections with respect to the
proposed provisional order or proposed confirmation
may be made,
and shall consider any representations or objections which are duly made
and not withdrawn.
(7) NLTA shall not confirm a provisional order with modifications
except –
(a) with the consent of the light rail operator to whom the
order relates; or
(b) after –
(i) serving on that light rail operator such notice of
the proposal to confirm the order with
modifications and in that notice, specifying
the period, not less than 28 days after the
date of service of the notice, within which
representations or objections with respect to the
proposed modifications may be made; and
(ii) considering any representations or objections
which are duly made and not withdrawn.
(8) In this section –
“provisional order” means an order under this section
which, if not previously confirmed in accordance with
subsection (5), shall cease to have effect at the end of such
period not exceeding 3 months, as is determined by or under
the order.