Occupational Safety And Health ActSixth Schedule, paragraph 10
10. Boiler
(a) What parts of seams, drums or headers are
covered by brickwork?
(b) Date of last exposure of such parts for the
purpose of examination
(c) What parts (if any) other than parts covered
by brickwork and mentioned above were inaccessible?
(d) What examination and tests were made? (if
there was any removal of brickwork, particulars should be given here)
(e) Condition of boiler—
State any defects materially External
affecting the maximum per- Internal
missible working pressure
[Issue 1] O2 – 74
Revised Laws of Mauritius
SIXTH SCHEDULE—continued