Offshore Petroleum Act 2021Section 61
61. Application for production licence
(1) No person shall make an application for a production
licence unless –
(a) (i) he is an exploration licensee; and
(ii) the sub-block to which the application relates is
declared a location; or
(b) he is a retention licensee.
(2) Subject to subsection (3), an application for a production
licence shall –
(a) be made in accordance with section 17(1); and
(b) in addition to the information required under
section 17(2), contain, where applicable, such other
information or document as the Department may
determine.
(3) An application made by an exploration licensee shall be
made –
(a) not later than 2 years as from the date of the declaration
of the location; or
(b) subject to subsection (4), not later than 4 years after
the date of the declaration of the location.
(4) The Department may allow a period under subsection (3)(b)
only on written application made by the exploration licensee within the
period of 2 years referred to in subsection (3)(a).
676 Acts 2021