Section 29: Consultation
consolidated text (as at 2013). juris shows the text as it was consolidated; it does not confirm that this is the law in force today.
29. Consultation
(1) A permit authority shall, in considering whether to grant a development permit, consult—
(a) where an application involves or is likely to involve any provider
of public utility services, with any such provider;
(b) where an application has or is likely to have significant environmental effects and the applicant is to be required to prepare a
preliminary environmental report or an EIA, with the Director;
[Issue 1] P11 – 22
Revised Laws of Mauritius
(c) where an application has or is likely to have a significant impact
on roads or traffic management, with the Ministry responsible
for the subject of roads;
(d) where the application has or is likely to have a significant impact
on agricultural development, with the Ministry responsible for
the subject of agriculture;
(e) where an application to develop land affects or is likely to affect
the land of or services provided by a neighbouring local
authority, with that neighbouring local authority;
(f) in any case where the Minister has issued a direction to a permit
authority to consult with any person named in the direction, with
that person;
(g) such other person as it may consider necessary.
(2) Where a permit authority consults any person in accordance with
subsection (1), it shall refer a copy of the application and all relevant
information to that person.
(3) The person shall, within 28 days of receipt of the application referred
to in subsection (2), communicate to the permit authority any comment, in
writing, it may have on that application.
(4) A permit authority shall, in determining an application made to it
under this Sub-part, consider any comment made under subsection (3).
(5) If, at the end of the period specified in subsection (3), the person
does not respond, it shall be presumed that that person does not have any
comment on the application and the permit authority may proceed to
determine the application.
(S. 29 not in operation.)
Ask juris about this section Official source
Questions this section answers
- Must the permit authority consult other bodies before deciding my development permit application?
- What happens if a consulted body does not respond within 28 days?