Sugar Industry Efficiency ActFifth Schedule, paragraph 1
1. Bagasse electricity production
(a) Steam generating equipment including boilers operating at not less
than 25 bars and associated auxiliaries intended to improve efficiency
of the steam generating process;
(b) bagasse drying;
(c) storage and handling of bagasse;
(d) (i) bagasse transport (ordinary); and
(ii) bagasse transport (specialised);
(e) steam saving prime-movers;
(f) electrical power generating equipment with an inlet steam pressure of
not less than 23 bars and a rated capacity of not less than 3 mega
Watt intended for efficient operation of the factory and for the use of
electrical prime-movers;
(g) process steam-saving equipment such as—
(i) heaters; and
(ii) pre-evaporator or other device leading to intensive bleeding and
steam economy;
(h) other equipment leading to improved steam/energy balance.