Sugar Industry Efficiency ActTwelfth Schedule, paragraph 8
8. Subject to paragraph 9, any applicant shall—
(a) endeavour to obtain all necessary clearances and permits, including
any Building and Land Use Permit, within a period of 2 years after
having been granted authority for land conversion;
(b) start the conversion of the land within a period of 6 months from
the date on which he obtained the last clearance or permit required
for the proposed conversion, failing which the authority shall lapse
automatically;
(c) complete the project in the manner specified in the authority granted
within a period of 5 years from the date on which he obtained the
last clearance or permit required for the conversion, failing which the
authority shall lapse automatically.