Town and Country Planning Act, No. 6 of 1954Section 15
15. Execution of an outline scheme
(1) Where an outline scheme has been brought into effect, the committee, subject to any directions given to it by the Minister on the advice of the
Board, shall be the authority responsible for executing and enforcing the
scheme.
(2) Where the committee is not the local authority, the local authority
shall be responsible for passing all plans for development works to the same
extent as it was responsible prior to the scheme coming into effect, but it
shall act in respect of the enforcing of the execution of the scheme in accordance with any direction given to it by the committee.
[S. 15 amended by s. 7 (4) (f) of Act 10 of 2018 w.e.f. 10 October 2018.]