Waste Water Management Authority ActSection 6A
6A. Wayleaves
(1) Where the Authority has reason to believe that it
is necessary or expedient for it to install, and keep installed,
the conduit on, under or over the land, the owner or occupier
of the land, shall be given a notice by the Authority requiring
him to grant the necessary wayleave within a period not
exceeding 21 days.
(2) Where the owner of the land is untraceable, the
Authority shall serve a notice posted up in a conspicuous
place on the land for a period not exceeding 21 days.
(3) Where there is no response from the owner or
occupier of the land following the issue of a notice under
subsections (1) and (2), the Board may conduct such works
as may be necessary and expedient in accordance with the
notice.
(4) Where the owner or occupier of the land, having
been given a notice, by the Authority requiring him to grant
the necessary wayleave within a period not exceeding 21 days
(cid:86)(cid:83)(cid:72)(cid:70)(cid:76)(cid:191)(cid:72)(cid:71)(cid:3)(cid:76)(cid:81)(cid:3)(cid:68)(cid:3)(cid:81)(cid:82)(cid:87)(cid:76)(cid:70)(cid:72)(cid:3)(cid:177)
(a) has objected to give the wayleave before
the end of that period; or
(b) has given the wayleave subject to terms
and conditions to which the Authority
objects; and
(c) where the Authority has been unable to
reach an agreement with the owner or
480 Acts 2021
occupier of the land within a period of
60 days from the date of issue of the
notice,
the Authority may apply to the Utility Regulatory Authority
for the determination of the notice to grant the wayleave.