Workers’ Rights Act 2019

Seventh Schedule, paragraph 1

SEVENTH SCHEDULE

Workers’ Rights Act 2019Seventh Schedule, paragraph 1

1. The Workfare Programme Fund shall be financed – (a) for the period starting on July 2023 and ending on June 2025, to the level of 0.75 per cent; (b) thereafter, to the level of 0.5 per cent, from the levy of one and a half per cent contributed by the employers under the Human Resource Development Act. PART II - FINANCING OF TRANSITION UNEMPLOYMENT BENEFIT

Start date not held: comes into operation on a date fixed by Proclamation, and juris holds no Proclamation for it.

unofficial consolidation (Ministry of Labour, as at 2025-08-09). juris shows this Act from the Ministry of Labour's consolidation as at 9 August 2025. It is not the official text and does not confirm that this is the law in force today.