120. Validity of Building and Land Use Permit
A Building and Land Use Permit shall lapse
within 2 years from the date of issue of the permit unless
any of the following works has been undertaken –
(a) for works at ground level, the external
walls of the building are raised to at least
600 millimetres above the floor slab;
(b) for a vertical extension to an existing
structure, the external walls of the building
are raised to at least 600 millimetres above
the floor slab of the lower floor;
(c) for a building with basement, the external
walls are raised to at least 600 millimetres
above the poured slab of the ground floor
above;
(d) for a timber construction, 20 per cent of
the framing structure on the level where
construction is being undertaken is lifted
and standing;
(e) for a steel construction, 20 per cent of the
steel framing structure on the level where
construction is being undertaken is lifted
and standing;
(f) the surrounding excavation of foundations
are backfilled to avoid water ponds; or
(g) such other works as may be prescribed.
210 Acts 2018
(iii) by inserting, after section 120, the following new
sections –
Ask juris about this section Official source
Questions this section answers
- How long is my Building and Land Use Permit valid before it lapses?
- What construction progress keeps my Building and Land Use Permit from lapsing?