Section 7: Issue of morcellement permit
consolidated text (as at 2017, amended since). juris shows the text as it was consolidated; it does not confirm that this is the law in force today.
7. Issue of morcellement permit
(1) The developer to whom a letter of intent has been issued under
section 6 shall, on completion of the infrastructural works, notify the Board
thereof and submit the documents specified in the guidelines referred to in
section 5 (5) (a).
(2) The Board may cause to be carried out such inspection as it thinks fit
to determine whether the infrastructural works have been carried out properly.
(3) Where the Board is satisfied that the developer has carried out the infrastructural works properly and produced a revised morcellement plan incorporating any amendment recommended by the Board, it shall, within 3
weeks of the date of notification under subsection (1), so report to the Minister who shall thereupon issue to the developer a morcellement permit.
(4) Notwithstanding subsection (3), where, in the case of a large investment project referred to in section 6 (7), the Board is satisfied, on application
being made by the developer, that infrastructural works have been completed on part of the land, the Board shall, within 2 weeks of the date of the
application, so report to the Minister who shall thereupon issue a morcellement permit in respect of that part of the land.
(5) Any morcellement permit referred to in subsection (3) or (4)—
(a) shall, subject to section 9, be issued by the Minister not later than
5 working days from the date reported to him by the Board; and
(b) may be issued on such terms and conditions as the Minister may
determine.
(6) Where the Board is not satisfied that the person has completed the
infrastructural works properly, it shall inform the person accordingly.
[S. 7 amended by s. 15 (4) (a) of Act 3 of 2007 w.e.f. 1 March 2007; repealed and replaced by
s. 15 (f) of Act 1 of 2009 w.e.f. 16 April 2009; amended by s. 22 (4) (c) of Act 22 of 2011
w.e.f. 1 July 2013; s. 36 (c) of Act 18 of 2016 w.e.f. 15 November 2016.]
Ask juris about this section Official source
Questions this section answers
- How do I get my morcellement permit after finishing the infrastructural works?
- How long does the Minister have to issue a morcellement permit after the Board reports?
- What happens if the Board is not satisfied I completed the infrastructural works properly?