Section 7A: Issue of morcellement permit in connection with schemes under the
consolidated text (as at 2017, amended since). juris shows the text as it was consolidated; it does not confirm that this is the law in force today.
7A. Issue of morcellement permit in connection with schemes under the
Sugar Industry Efficiency Act
(1) Where land is to be transferred in relation to a VRS, ERS or factory
closure referred to in section 26 (1) of the Sugar Industry Efficiency Act, the
transferor shall make an application for a morcellement permit in respect of
that land.
(2) The Board shall, within a period of 6 weeks from the effective date of
an application under subsection (1), make a decision on whether to issue a
letter of intent.
(3) Every member of the Board shall convey his stand on the application
within one month of the effective date referred to in subsection (2), failing
which he shall be deemed to have no objection to the issue of the letter of
intent.
M67 – 6 (1) [Issue 9]
Morcellement Act
(4) The transferor shall, within a period of 15 months from the date of
issue of the letter of intent, complete the infrastructural works properly to
the satisfaction of the Board.
(5) Where the transferor fails to comply with subsection (4), without any
reasonable excuse or justification, the burden of proving which shall lie on
him, he shall commit an offence and shall, on conviction, be liable to a fine
not exceeding 100,000 rupees for every calendar month of delay in the
completion of the infrastructural works.
continued on page M67 – 5
[Issue 9] M67 – 6 (2)
Revised Laws of Mauritius
(6) (a) For the purpose of this section, the Board may, in addition to the
members specified in section 4 (2), include a maximum of 3 co-opted members.
(b) A co-opted member shall have no right to vote.
(7) In this section—
“effective date” means the date by which the Board shall have
obtained all the information, particulars and documents required from the
transferor and which date shall be communicated to the transferor;
“transferor” has the meaning assigned to the word “developer” in this
Act.
[S. 7A inserted by s. 15 (4) (b) of Act 3 of 2007 w.e.f. 1 March 2007.]